With a view to strengthening the electrical system and improving the reliability and continuity of supply during the summer of 2026/2027, the president of Paraguay’s National Electricity Administration (ANDE), Félix Sosa, evaluated the progress of the works and the coordination of the execution during a meeting with the Technical Management, the Distribution, Regional Management and Telematics directorates, as well as heads of the East, South, North, Centre, Central, Chaco and Metropolitan Area regions.
During the meeting, officials reviewed the main infrastructure projects planned for the coming summer months. These include the expansion of the transformation capacity of several substations, as well as the construction and reinforcement of new Medium Voltage lines across key areas of the country.
Solar panels in Paraguay are becoming another option for homeowners seeking reliable electricity, businesses managing energy consumption and rural properties beyond the electricity network. Even apartment residents and renters have alternatives for keeping essential appliances running. Read more about these options in The Asunción Times’ Ultimate Guide to solar power in Paraguay.
Key substations set for commissioning and capacity boosts
The latest works by ANDE include the commissioning of the San José de los Arroyos Substation, which will benefit users in that city and Nueva Londres. Officials also confirmed the power expansion of the Campo Dos Substation in Caaguazú, which will improve the electricity supply in José Eulogio Estigarribia, Raúl Arsenio Oviedo and José Domingo Ocampos.
The commissioning of the INERAM substations in the Metropolitan area and the Manitoba substation in the department of San Pedro is also planned. In addition, ANDE will carry out a power increase of the Cerro Corá Substation in Amambay to support local demand.
New medium voltage lines and feeder upgrades across regions
The plan also includes the commissioning of a new 66-kilometre Medium Voltage line from the Loma Plata Substation. This line will benefit Tte. Montanía and nearby towns in the department of Boquerón, extending more reliable service into the Chaco area.
Construction and reinforcement work is also being carried out on several 23,000 Volt feeders in different sectors of the country. At the same time, ANDE is advancing the modernisation of the distribution networks with the replacement of bare conductors with protected and pre-assembled cables in several 23,000 Volt feeders.
Strategic action to meet rising summer demand
With these actions, ANDE is advancing in the execution of strategic works to anticipate the growth in demand. The focus remains on reinforcing the most demanding sectors and improving the response capacity of the electrical system.
These coordinated efforts aim to ensure a more resilient supply as consumption rises during the months of high temperatures, giving residents and businesses greater confidence in continuous power throughout the 2026/2027 summer period.